The short answer
A condo renovation in Vancouver runs through eight stages: the building's documents, design, a hazardous materials inspection, the strata's decision, permits, ordering, the work on site and the final documents. BC law gives a council 4 weeks to hold a requested hearing and one more week to decide in writing. Our published time for a kitchen in a North Shore house is 10 to 16 weeks from demolition to completion.
What sets the total length
The total is the sum of eight stages, and the building work is only one of them. Four stages happen before any work starts in the unit: getting the building's documents, design, the hazardous materials inspection and the strata's decision. Permits and ordering follow. Then comes the work on site, and last the documents that finish the job.
Different parties control different stages. You control how fast you choose a layout and products. The strata council controls the date of its decision. The City of Vancouver controls its permits. Suppliers control how long an order takes. The contractor controls the work on site, inside the hours your building allows.
For that reason we give a start date only after the strata's written approval has arrived and the permit question is settled with the City.
The eight stages, what sets each length, and who controls it
The table lists the stages in order. Every week figure in it is one of our published figures for a house on the North Shore. The legal deadlines come from BC's Strata Property Act.
| Stage | What sets the length | Who controls it |
|---|---|---|
| 1. The building's documents | The strata's deadline to provide them: one week for bylaws and rules, 2 weeks for other records (Strata Property Act, s. 36(3)) | The strata, once you ask in writing |
| 2. Design, products and the request package | How fast the layout and the products are chosen. Our published design stage for a house kitchen is 3 weeks | You and your contractor |
| 3. Hazardous materials inspection | Booking the qualified person, the sampling and the written report. Removal comes next if the report finds a hazardous material | You and your contractor. A licensed contractor removes asbestos |
| 4. The strata's decision | The council's meeting dates. After a written hearing request, the council has 4 weeks to hold the hearing and one more week to decide in writing (s. 34.1) | The strata council |
| 5. Permits | The City of Vancouver's own processing. We state no City time on this page | The City. The licensed electrical and gas contractors apply for their permits |
| 6. Ordering | The product with the longest wait. Our published wait for a cabinet order is 8 to 12 weeks | The suppliers. You control the day the order is placed |
| 7. Work on site | The scope, the working hours and the elevator bookings. Our published house figures: a kitchen with permits takes 10 to 16 weeks from demolition to completion, a single bathroom 4 to 6 weeks | The contractor, inside your building's rules |
| 8. Final documents | The papers the approval asks for at the end, such as permit copies and photos | You and your contractor |
Stage 1: the bylaws and the strata plan
Ask the strata in writing for its bylaws, its rules, any renovation form or alteration agreement, and the registered strata plan. An alteration agreement is the written permission with conditions that some stratas ask an owner to sign. The strata plan is the registered drawing that shows where your unit ends and the common property begins.
The law sets the wait. Under section 36(3) of the Strata Property Act, the strata must provide its bylaws and rules within one week of an owner's request, and its other records within 2 weeks.
These documents decide the rest of the schedule. They state which work needs approval in your building, what the request must contain, and the hours when work is allowed.
Stage 2: design and the request package
The design stage ends when you have a fixed layout and a list of chosen products. The strata request needs both, because a council approves a described scope with named products.
Our project timeline calculator gives 3 weeks of design and planning for a kitchen in a house and 2 weeks for a bathroom. Those are house figures. In a condo, the same stage also produces the request package: the written scope, drawings, product sheets, the contractor's documents and the planned dates.
A complete package leaves the council fewer questions to ask. If the request leaves out a document your building's form lists, the council can ask for it, and its answer may then wait for a later meeting.
Stage 3: the hazardous materials inspection
The inspection must be done before work begins, so book it during the design stage. Section 20.112 of the Occupational Health and Safety Regulation requires the employers responsible for a renovation, and the owner, to ensure that a qualified person inspects the building for hazardous materials before the work starts. WorkSafeBC says a home built before 1990 is likely to contain some asbestos.
The result changes the schedule in one of two ways. If the report finds nothing hazardous in the areas the work will disturb, the work can go ahead. If it finds asbestos or another hazardous material, section 20.112(7) and (8) stop any work that may disturb that material until it is safely contained or removed and a qualified person has confirmed this in writing.
We have no published figure for how long an inspection or a removal takes, so this page gives none. Send the report to the strata with your request.
Stage 4: the strata's decision
An ordinary renovation request sent to the strata manager is answered on the council's own meeting schedule, which each council sets. We publish no usual approval time, because we have no source for one. Ask the manager for the date of the next council meeting and the last day to add an item to its agenda.
The Strata Property Act sets deadlines once you ask for a hearing. Under section 34.1, an owner may request a hearing at a council meeting by writing to the council and stating the reason. The council must hold a meeting to hear the owner within 4 weeks after the request. If the purpose of the hearing is to get a decision, the council must give a written decision within one week after the hearing. From a written hearing request to a written decision, the longest wait the Act allows is 5 weeks.
An approval can come with conditions, such as an agreement on expenses that Standard Bylaw 5(2) lets the strata require. Leave time to meet them before the first working day.
Stage 5: permits
Inside the City of Vancouver, the City issues electrical and gas permits. Technical Safety BC, the body that runs BC's Safety Standards Act, lists the City of Vancouver among 10 municipalities that issue their own electrical and gas permits. It also says that when you hire a licensed contractor, the contractor applies for the permit on your behalf.
The City sets its own processing times for these permits and for building permits. Its website refused our automated requests on October 4, 2026, so we could read none of its pages and this page states no City time. We ask the City about each project and add its answer to the schedule.
Stage 6: ordering
The product with the longest wait sets the length of this stage. In a kitchen that product is the cabinets. Our published wait for a cabinet order is 8 to 12 weeks.
The day the order is placed is your decision. An order placed before the strata's written approval saves time if the council approves the request unchanged. If the council asks for a change to the layout, a made-to-measure order may no longer fit, and you pay to change it. We tell you which items are safe to order early and which should wait for the approval letter.
Stage 7: the work on site
Our published durations show how long the building work takes in a house on the North Shore. A kitchen renovation with permits takes 10 to 16 weeks from demolition to completion. A single bathroom takes 4 to 6 weeks, and a bathroom with plumbing relocation takes 6 to 10 weeks.
Our timeline calculator divides a house kitchen into stages that add up to 16 weeks, of which 10 are on site. Its bathroom stages add up to 10 weeks, of which 6 are on site. The calculator holds no stage for strata approval.
These are house figures. They assume a crew that can work a full day and bring materials to the door.
Why the same scope takes longer on site in a condo
Four conditions add days on site in a condo. Each one is set by your building, so we attach no number to any of them.
- Working hours. Your building's bylaws, rules or alteration agreement set the days and hours when work is allowed. Fewer hours in a day mean more days for the same work.
- Elevator bookings. Materials, tools and waste travel by elevator. Where the building requires a booking, each delivery and each waste removal has to fit a booked time.
- Deliveries. A condo has a shared loading area and no room to store a full kitchen, so materials arrive in smaller loads on the days they are needed.
- Common property. Work on a shared pipe, a duct or any other common property waits for the strata's written approval under Standard Bylaw 6. If a change of that kind appears after the job has started, the work on that part stops until the approval arrives.
What an owner can do early to shorten the total
Most of the time an owner can save is in the stages before the work. Each step below can start in the first week.
- Request the bylaws, the rules, the renovation form and the strata plan on the first day. The one-week and 2-week deadlines in section 36(3) start with your request.
- Ask the strata manager for the council's next meeting date and the last day to add an item to its agenda. Plan the request package to arrive before that day.
- Book the hazardous materials inspection while the design is being drawn, so that the report is ready to send with the request.
- Choose the flooring, fixtures and appliances before the request goes in. A council that receives product sheets has fewer questions to ask.
- Send one complete request. Use the same scope wording in the contract and in the request, so the council approves the work that will be built.
- If a council meeting passes with no answer, send a written hearing request under section 34.1. It starts the 4-week and one-week deadlines.
- Decide with your contractor which orders can be placed before the approval letter and which should wait.
- Ask the building how far ahead elevator times must be booked, and book the delivery days as soon as the start date is fixed.
Which stages can run at the same time
Some stages overlap, and a schedule that uses the overlap is shorter. The inspection can run during design. The permit question can go to the City while the council is reading the request. Orders for items that no council condition could change can be placed during the wait for approval.
Two stages must follow each other in order. Standard Bylaw 5(1) requires the strata's written approval before the alteration is made, so demolition waits for the approval letter. And any hazardous material named in the report is contained or removed before the work around it begins.
We write the schedule as a list of dated stages and show which dates depend on the council and on the City. When one of those dates moves, we send a revised schedule.
Sources
- Strata Property Act, SBC 1998, c. 43 (sections 34.1, 36, 125 and 130), read October 4, 2026
- Strata Property Act, Schedule of Standard Bylaws (Bylaws 5 and 6), read October 4, 2026
- Strata Property Regulation, B.C. Reg. 43/2000 (section 7.1, maximum fines), read October 4, 2026
- Occupational Health and Safety Regulation, B.C. Reg. 296/97, Part 20 (section 20.112, hazardous materials), read October 4, 2026
- WorkSafeBC, Have your home tested for asbestos before reno, demo, or maintenance work, read October 4, 2026
- Technical Safety BC, Jurisdiction (local governments that issue their own electrical and gas permits), read October 4, 2026
- Technical Safety BC, Homeowner Electrical Permits, read October 4, 2026
- Civil Resolution Tribunal, Strata Property, read October 4, 2026
Frequently asked questions
Which stages of a condo renovation can run at the same time?
The hazardous materials inspection can run during the design stage of a condo renovation, and the permit question can go to the City while the council reads the request. Section 20.112 of the Occupational Health and Safety Regulation only requires that the inspection happen before work begins. Demolition has a fixed place in the order. Standard Bylaw 5(1) requires the strata's written approval before the alteration is made, so it waits for the approval letter.
Does RealDream's timeline calculator include time for strata approval?
Our timeline calculator holds no stage for strata approval, because it was built on our published figures for houses. Its kitchen stages add up to 16 weeks, of which 10 are on site, and its bathroom stages add up to 10 weeks, of which 6 are on site. For a condo, add the wait for the council's written decision and the limits your building sets on working hours and deliveries.
How long does a bathroom with moved plumbing take in a house?
Our published time for a bathroom with plumbing relocation in a North Shore house is 6 to 10 weeks from demolition to completion, compared with 4 to 6 weeks for a standard single bathroom. Both are house figures. In a condo, moving a drain can also involve a shared pipe, which is common property, and Standard Bylaw 6 requires the strata's written approval before common property is altered.
Can demolition start in a condo while the cabinets are being made?
Demolition in a condo can start while the cabinets are being made only if the strata's written approval has already arrived. Our published wait for a cabinet order is 8 to 12 weeks, and our timeline calculator gives demolition one week in a house kitchen. Starting demolition at the beginning of that wait leaves the unit without a kitchen for longer, so we time it to end as the cabinets arrive.
Does finding asbestos change the length of a condo renovation?
Finding asbestos adds a removal step before the renovation of a condo can continue. Under section 20.112(7) and (8) of the Occupational Health and Safety Regulation, no work that may disturb the identified material can be carried out until it is safely contained or removed, and a qualified person must confirm that in writing. We have no published duration for removal, so we schedule it once the report shows the quantity.
What happens to the schedule if workers find a suspect material during demolition?
Work around a suspect material found during demolition stops until the material has been identified. Section 20.112(6) of the Occupational Health and Safety Regulation says that if material that may be hazardous is discovered after the written confirmation, a qualified person must sample it, identify it and report in writing. The rest of the condo renovation continues only in areas where the work cannot disturb that material.
How much time does a strata refusal add to a condo renovation?
A strata refusal adds at least the time of a hearing to a condo renovation, and more if the dispute goes to the Civil Resolution Tribunal. Section 34.1 of the Strata Property Act gives the council 4 weeks to hold a requested hearing and one week to decide in writing. The tribunal's strata page says it can take several months for an application to be reviewed and a Dispute Notice issued.
Should electrical work in a condo start before the permit is in place?
Electrical work in a condo that needs a permit should start only after the permit is in place. Technical Safety BC says that when you hire a licensed contractor, the contractor applies for the permit on your behalf, and it tells owners to check that a permit is in place before work begins. Inside Vancouver the City issues the permit, so ask your contractor to show it to you.
Can a contractor work longer days to finish a condo renovation sooner?
A contractor can work only during the hours your condo building allows, so longer days are possible only inside those hours. Each building sets its hours in its bylaws, rules or alteration agreement. Working outside them can cost the owner a fine: the Strata Property Regulation lets a strata set fines of up to $200 for each contravention of a bylaw and up to $50 for each contravention of a rule.
How long is the design stage for a kitchen or bathroom renovation?
Our timeline calculator gives 3 weeks of design and planning for a kitchen renovation in a house and 2 weeks for a bathroom. Those are our published house figures. In a condo, the design stage also has to produce the strata request package, with drawings and product sheets, and it can only be finished after you have read the bylaws, which the strata must provide within one week of a request.