The short answer
A condo renovation in Vancouver can need two separate permissions: the strata's written approval and permits from the City of Vancouver. Technical Safety BC lists the City of Vancouver among 10 municipalities that issue their own electrical and gas permits. It also states that owners of a strata cannot obtain homeowner permits and must hire a licensed contractor. Ask the City which permits your scope of work needs.
Strata approval and City permits are two separate permissions
A condo renovation can need permission from two bodies, and each one decides for itself. The strata corporation applies its bylaws. The City of Vancouver applies its building, electrical and gas rules.
You need each one for the work it covers. The strata's approval letter answers the building's bylaws, and a City permit answers the City's rules. Under Standard Bylaw 5(1), an owner must have the strata's written approval before altering the items on its list, which include the structure of the building and the parts of the unit the strata must insure.
The table shows each permission, who gives it, and where the rule is written.
| Permission or duty | Who gives it or carries it | Where the rule is written |
|---|---|---|
| Approval of the alteration | The strata corporation, in writing | Standard Bylaws 5 and 6, or your building's own bylaws |
| Electrical permit | The City of Vancouver. A licensed contractor applies | Technical Safety BC's list of municipalities that issue their own permits |
| Gas permit | The City of Vancouver, inside the limits set for local governments | The same list, and Technical Safety BC's Jurisdiction page |
| Building permit | The City of Vancouver | The City's own building by-law. Ask the City which work needs one |
| Hazardous materials inspection before work begins | The owner and the employers responsible for the work | Occupational Health and Safety Regulation, section 20.112 |
| Contractor licences for electrical and gas work | Technical Safety BC | Technical Safety BC's Jurisdiction page |
Electrical and gas permits come from the City
In most of BC, Technical Safety BC issues electrical and gas permits. It is the body that runs the province's Safety Standards Act. The City of Vancouver is one of the exceptions.
Technical Safety BC's Jurisdiction page states: "There are 10 municipalities that are delegated portions of the Safety Standards Act to issue electrical and/or gas permits and to perform assessments. Technical Safety BC typically does not issue permits or perform assessments for electrical or gas work and equipment in these areas." The list on that page includes the City of Vancouver for both electrical and gas.
Its page on electrical installation permits repeats the point. Technical Safety BC issues those permits "unless you are located in one of the following areas, in which case you should check with the municipality or district", and Vancouver is in the list that follows.
For gas, the same Jurisdiction page sets a limit on what a local government can issue. For a building other than a fully detached house, a local government can issue a natural gas installation permit where the gas meter pressure is 2 psi (14 kPa) or less and the total connected load is 409,600 BTU per hour (120 kW) or less. Technical Safety BC keeps jurisdiction over other regulated gases, such as propane.
Licensing stays with the province. The page says that although these 10 jurisdictions have oversight for electrical or gas, "Technical Safety BC still oversees contractor licensing and certification of qualified individuals".
A strata owner hires a licensed contractor
A condo owner cannot do electrical or gas work under a homeowner permit from Technical Safety BC. Both of its homeowner permit pages state: "Owners of a strata, non-strata duplex, and those operating a business from their home cannot obtain homeowner permits and must hire a licensed contractor." That is Technical Safety BC's rule for the permits it issues. The City of Vancouver issues its own permits, so confirm with the City who may apply for one.
The same pages give examples of work that needs a permit under the provincial rules. For electrical work, the examples include replacing light fixtures, installing or moving light switches or electrical outlets, and connecting permanently installed equipment such as a dishwasher, a range hood or a heat pump. For gas, they include installing or replacing a gas range or cooktop and installing or replacing gas piping.
The contractor handles the application. Technical Safety BC says: "if you are hiring a licensed contractor, your contractor will apply on your behalf. Check to ensure there is one in place before work begins." On its own electrical permits, a Field Safety Representative, a certified person who can declare that finished electrical work meets the rules, must be named on every application.
Two more sentences from Technical Safety BC explain why this matters to an owner. The first: "Permits are a legal requirement in BC and are often necessary for home insurance purposes." The second: "If you do not obtain a permit when required by law to do so, you may face consequences that range from a warning to a monetary penalty or prosecution."
Building permits: Vancouver has its own building by-law
The BC Building Code is the Province's set of rules for new construction, alterations and repairs. A condo inside the City of Vancouver falls under a different document. The Province's page for the BC Building Code 2024 states: "Note: BC Codes don't apply in the City of Vancouver which has its own building bylaw."
This matters when you read about permits online. An article that quotes the BC Building Code, or the permit rules of another municipality, describes a different set of rules from the one the City of Vancouver applies. The current provincial code came into effect on March 8, 2024, and it applies in BC outside the City of Vancouver.
Which condo work needs a City building permit, what the permit costs and how long it takes are questions only the City can answer. The next section explains why this page gives no answer to them.
What we could not verify, and how to ask the City
The City of Vancouver's website refused our automated requests on October 4, 2026. We used no copy of its pages from any other website. For that reason this page states no City permit fee, no processing time and no list of work that is exempt from a permit. We publish only figures we have read in their primary source.
Ask the City's permit office directly, in writing, and keep the reply. The City's open data page for issued building permits lists two City pages by title, "When you need a permit" and "Building permit", as places for further information. Send the questions below with a description of your work.
- Does this scope of work in a strata unit need a building permit? Describe each change: walls, plumbing, electrical, flooring, fixtures.
- Does it need an electrical permit, a gas permit or any other trade permit, and who is allowed to apply for each one?
- What drawings or documents does the application need?
- What is the fee for each permit, and how is it calculated?
- What is the current processing time?
- Which inspections does the City carry out, and at which points in the work?
- Does the City ask for a letter from the strata corporation with the application?
The inspection the law requires before work begins
One legal step applies before any renovation work, with or without a permit. Section 20.112(2) of the Occupational Health and Safety Regulation says that before work begins on the renovation of a building, all employers responsible for that work, and the owner, must ensure that a qualified person inspects the building and the worksite to identify the hazardous materials, if any.
The qualified person writes a report, and the employers and the owner must make sure it is available at the worksite. If the report identifies a hazardous material, no work that may disturb it can be carried out until it is safely contained or removed, and a qualified person has confirmed that in writing (section 20.112(7) and (8)).
Asbestos removal has its own paperwork. WorkSafeBC states that a notice of project must be submitted to WorkSafeBC for all asbestos work, and that since January 1, 2024, asbestos abatement contractors, the companies that remove or contain asbestos, must be licensed to operate in BC.
Where BC's strata law mentions building permits
The Strata Property Act links strata approval and building permits in one section. Section 70 covers the removal of all or part of a wall that is a common boundary between adjoining strata lots, for example when one owner joins two units. Section 70(3) says the owner must give copies of any required building permits to the strata corporation when seeking its approval.
Section 70(2) also links the strata's answer to the building rules. The strata must approve the removal unless it fails to comply with a building regulation or any applicable municipal bylaws, or interferes with utilities or other services to another strata lot or the common property.
For other work, your building's own bylaws or its alteration agreement, the written permission with conditions that some stratas ask an owner to sign, may ask for permit copies. Read them, and ask the strata manager in writing what the council wants to see and when.
A public record of issued building permits
The City publishes a data set called "Issued building permits" on its open data site, under the Open Government Licence - Vancouver. Its description says it includes information on all building permits issued by the City, starting in 2017, and that the current year's extract is updated daily. The description adds that the data shows a permit as it was issued and leaves out later changes.
When we queried the data set on October 4, 2026, it held 52,248 records, with issue dates from January 3, 2017 to October 2, 2026. Each record gives the address, the issue date, the type of work, the use of the property and the applicant. Records from 2018 onward also carry a description of the project.
The type of work field takes six values. On that date, 25,846 records were marked "Addition / Alteration", 11,964 "New Building", 7,128 "Demolition / Deconstruction", 6,750 "Salvage and Abatement", 498 "Temporary Building / Structure" and 62 "Outdoor Uses (No Buildings Proposed)". Of the addition and alteration records, 5,479 carried the specific use category "Multiple Dwelling". That label is the City's own and the data set gives it no definition, so we draw no conclusion about which buildings it covers.
The data set has one practical use for a condo owner. Search it for your building's street address and read the project descriptions of the permits issued there. You will see whether permits have been issued for work in your own building and how that work was described. Treat the result as a record of past permits, and ask the City what your own work needs.
How we handle permits on a condo job
We ask the City about the scope of each project before we give a start date, and we keep its reply with the job's documents. The licensed electrical and gas contractors apply for their own permits, and we check that each permit is in place before that trade starts.
We tell the strata which permits the work needs in the renovation request, and we send copies where the building's bylaws or approval ask for them. At the end you receive the permits and inspection records for the file you keep for the unit, beside the strata's approval letter and the hazardous materials report.
Sources
- Technical Safety BC, Jurisdiction (local governments that issue their own electrical and gas permits), read October 4, 2026
- Technical Safety BC, Electrical Installation Permits, read October 4, 2026
- Technical Safety BC, Homeowner Permits, read October 4, 2026
- Technical Safety BC, Homeowner Electrical Permits, read October 4, 2026
- Technical Safety BC, Homeowner Gas Permits, read October 4, 2026
- Province of BC, BC Building Code 2024 (published March 10, 2025), read October 4, 2026
- Occupational Health and Safety Regulation, B.C. Reg. 296/97, Part 20 (section 20.112, hazardous materials), read October 4, 2026
- WorkSafeBC, Asbestos, read October 4, 2026
- WorkSafeBC, Asbestos training, certification and licensing, read October 4, 2026
- Strata Property Act, SBC 1998, c. 43 (section 70), read October 4, 2026
- Strata Property Act, Schedule of Standard Bylaws (Bylaws 5 and 6), read October 4, 2026
- City of Vancouver Open Data Portal, Issued building permits (Open Government Licence - Vancouver), queried October 4, 2026
Frequently asked questions
Which BC municipalities issue their own electrical or gas permits?
Ten BC municipalities issue their own electrical or gas permits, according to Technical Safety BC's Jurisdiction page. Burnaby, Maple Ridge, the City of North Vancouver, the District of North Vancouver and the City of Vancouver issue both. Surrey, Victoria and the District of West Vancouver issue electrical permits only. Kelowna and Richmond issue gas permits only. Elsewhere in BC, Technical Safety BC issues these permits itself.
Can a city issue a gas permit for any size of gas system in a condo building?
A local government's power to issue gas permits has a size limit. Technical Safety BC's Jurisdiction page says that for a building other than a fully detached house, a local government can issue a natural gas installation permit where the gas meter pressure is 2 psi (14 kPa) or less and the total connected load is 409,600 BTU per hour (120 kW) or less. Technical Safety BC keeps jurisdiction over other regulated gases, such as propane.
Who licenses the electrical and gas contractors who work in Vancouver?
Technical Safety BC licenses electrical and gas contractors across the province, including those who work in Vancouver. Its Jurisdiction page says that although 10 municipalities have oversight for electrical or gas permits, Technical Safety BC still oversees contractor licensing and the certification of qualified individuals. So a Vancouver condo owner deals with two bodies: the City for the permit and Technical Safety BC's licence for the contractor.
What can happen if electrical work is done without a permit in BC?
Electrical work done without a required permit in BC can lead to a penalty. Technical Safety BC's page on electrical installation permits says that if you do not obtain a permit when required by law, you may face consequences that range from a warning to a monetary penalty or prosecution. Its homeowner permits page adds that permits are often necessary for home insurance purposes, so ask your contractor for the permit before work starts.
When did the current BC Building Code take effect, and where does it apply?
The BC Building Code 2024 came into effect on March 8, 2024, and it applies to projects with building permits applied for after that date. It applies in BC outside the City of Vancouver. The Province's page states that BC Codes do not apply in the City of Vancouver, which has its own building bylaw, so a Vancouver condo owner should ask the City which requirements apply.
What does the City of Vancouver's issued building permits data set contain?
The City of Vancouver's "Issued building permits" data set holds information on all building permits the City has issued, starting in 2017. On October 4, 2026 it held 52,248 records, with issue dates from January 3, 2017 to October 2, 2026. Each record gives the address, the issue date and the type of work. The City publishes it under the Open Government Licence - Vancouver and updates the current year daily.
How many of Vancouver's issued building permits are for additions or alterations?
On October 4, 2026, 25,846 of the 52,248 records in the City of Vancouver's issued building permits data set were marked "Addition / Alteration" in the type of work field. The other five values were "New Building" with 11,964 records, "Demolition / Deconstruction" with 7,128, "Salvage and Abatement" with 6,750, "Temporary Building / Structure" with 498 and "Outdoor Uses (No Buildings Proposed)" with 62. The counts cover every type of property together.
Is the hazardous materials inspection a permit?
The hazardous materials inspection is a legal duty under BC's workplace safety rules, and it stands apart from every permit. Section 20.112(2) of the Occupational Health and Safety Regulation requires the employers responsible for a renovation, and the owner, to ensure a qualified person inspects the building before work begins. Where the work includes asbestos removal, WorkSafeBC states that a notice of project must be submitted to WorkSafeBC.
Why does this page give no City of Vancouver permit fee or processing time?
This page gives no City of Vancouver permit fee or processing time because we could not read the City's own pages. The City's website refused our automated requests on October 4, 2026, and we publish only figures we have read in their primary source. Ask the City's permit office in writing for the current fee and processing time for your scope of work, and keep the reply.
Does Vancouver's open data show how long my building permit will take?
Vancouver's open data records how long past permits took. An estimate for a new application has to come from the City. The issued building permits data set has a field named PermitElapsedDays, which measures the number of days from the creation of a permit number until the permit was issued, weekends and holidays included. We have derived no average from it. Ask the City for its current processing time.