How to Write a Strata Renovation Request in BC, With a Sample Letter

A strata council can approve a renovation at one meeting when the request answers its questions in advance. This page sets out the few things BC law requires of a request, the nine parts of a complete one, and a sample letter you can fill in. It follows the Province's Standard Bylaws. If your building has its own application form, use that form and attach the same information.

By Nima Gerani, Founder, RealDream Contracting
October 4, 2026 11 min read

The short answer

A renovation request to a BC strata council should be in writing and should let the council decide at one meeting. Give the unit and owner, the work listed against each bylaw item it touches, drawings, the pipes and wires affected, the contractor's documents, the dates and hours, and the plan to protect common areas. Standard Bylaw 5 requires the approval itself to be in writing.

Note: The sample letter is a draft to adapt, written by a renovation contractor. Your building may have its own application form or alteration agreement, and its filed bylaws apply to your unit. Section numbers were read on October 4, 2026. Get legal advice before signing an agreement with your strata.

What the law requires of the request

The law asks for little. Standard Bylaws 5(1) and 6(1) say an owner must obtain the written approval of the strata corporation before making an alteration. The approval must be written. The Standard Bylaws say nothing about the form of the request, so a letter or an email is enough unless your building's own bylaws set a form.

The request comes from the owner. Both bylaws begin with the words "An owner must obtain". A contractor can prepare the documents, and the owner signs and sends them.

The Act does say how a document is given to a strata corporation. Under section 63(1), a document may be left with a council member, mailed to the strata's most recent mailing address on file in the land title office, emailed or faxed to the strata's own address or to one a council member has provided for that purpose, or put in the strata's mail slot or mailbox. Section 63(2) treats a document sent by mail, fax, email or mail slot as given 4 days after it is sent. Write the sending date on the letter and keep proof of it.

One later document has stricter rules. If the council leaves your request unanswered, section 34.1 of the Act lets you request a hearing at a council meeting. That request must be an application in writing "stating the reason for the request". Section 4.01 of the Strata Property Regulation defines the hearing as an opportunity to be heard in person at a council meeting.

Three documents to get before you write

Ask the strata for three things first. Each one changes what the letter says.

  • The current bylaws and rules. The strata must provide them within one week of an owner's request (Act, s. 36(3)).
  • The registered strata plan. The strata must keep a copy (s. 35(2)(b)) and must provide records on that list within 2 weeks of an owner's request (s. 36(3)). The plan shows where your unit ends and which parts are limited common property, meaning common property set aside for the use of one or more units.
  • The building's own renovation form or alteration agreement, if it has one, with its list of the documents a contractor must show.

The nine parts of a complete request

A complete request has nine parts. The table gives each part and the question it answers for the council. Where a part is based on the law, the section number is in the right-hand column. The other parts come from our working method, so match them to your building's own list.

Parts of a strata renovation request
Part What to write Why the council needs it
1. Owner and unit Owner's full name, unit number, strata lot number and strata plan number The approval is given to an owner for one strata lot (Standard Bylaw 5(1))
2. Scope of work Room by room: what is removed, what is installed, what stays The written approval covers the alteration described, so the description sets its limits
3. Bylaw items touched Each part of the work beside the item of Bylaw 5(1) or Bylaw 6 it falls under Only Bylaw 5 says approval must not be unreasonably withheld, so the council needs to know which bylaw applies
4. Pipes, wires and ducts Each one the work touches, and whether it serves other units Those that serve other units are common property (Act, s. 1)
5. Drawings and products A floor plan marked with the changes, and the makers' product sheets A council member who has never seen the unit can follow the change
6. Contractor Company name, contact person, and the documents your building's bylaws list Each building sets its own contractor requirements
7. Dates and hours Planned start and finish dates, and the working hours your building's bylaws or rules set Standard Bylaw 3(1) forbids unreasonable noise. Your building's text sets the hours
8. Common areas How hallways and the elevator will be protected, and how materials and waste will move Standard Bylaw 3(2) forbids damage to the common property
9. Expenses A request for the strata's agreement on expenses, so you can read it Bylaws 5(2) and 6(2) let the strata require the agreement as a condition

Scope, bylaw items and pipes: how to write each one

Write the scope so that it can be checked against the finished work. In place of "Renovate bathroom", write: "Remove the tub, toilet, vanity and floor tile. Install a new tub, toilet and vanity in the same positions. Install new floor tile over a sound-reducing layer." The council can then see what will change and what will stay.

Then sort the scope by bylaw item. Standard Bylaw 5(1) has seven items, from (a) the structure of the building to (g) the parts of the unit the strata must insure. Bylaw 6 covers common property and limited common property. Naming the item beside each piece of work shows the council which bylaw it is deciding under, and the two differ: only Bylaw 5 says the strata "must not unreasonably withhold its approval".

Give pipes, wires and ducts their own heading. The Act's definition of common property includes those that sit inside a boundary wall, floor or ceiling, and those inside the unit that are capable of being used, and intended to be used, by another unit or the common property. State which ones the work touches and which it leaves alone. If the work touches none that serve other units, say so in one sentence.

Contractor, dates, common areas and expenses

For the contractor, send exactly what your building's bylaws, rules or alteration agreement list. Each building sets its own list. Ask for it in writing and attach each document by name.

For dates and hours, quote the building's own text. Write the bylaw or rule number and the hours it gives, then state that the work will stay inside them. Give a planned start date that falls after the council's next meeting.

For common areas, describe the protection in plain steps: what will cover the hallway floor and the elevator walls, which entrance materials will come through, where waste will go, and who cleans the route at the end of each day.

The expenses part needs care. Bylaws 5(2) and 6(2) allow the strata to require, as a condition of approval, that the owner "agree, in writing, to take responsibility for any expenses relating to the alteration". Ask in your letter for the agreement the strata uses, and read it before you sign.

The agreement stays with the unit's records. When a unit is sold, the strata gives the buyer an Information Certificate, a form that lists fees, debts and agreements on the unit. Section 59(3)(c) of the Act requires it to disclose "any agreements under which the owner takes responsibility for expenses relating to alterations". A buyer will read what you signed, so keep the agreement, the approval letter and the drawings together.

A sample request letter

Copy the lines below and replace each pair of square brackets with your own details. Change the bylaw numbers to match your building's filed bylaws. Delete any line that does not apply to your work.

  • To: The strata council, Strata Plan [plan number], care of [strata manager's name and company]
  • From: [owner's full name], owner of unit [unit number], strata lot [strata lot number]
  • Date sent: [date], by [email or mail] to [address]
  • Subject: Request for written approval of an alteration under Bylaws [5 and 6, or your building's bylaw numbers]
  • I am asking for the strata corporation's written approval of the renovation described in this letter. No work will start before I hold that approval in writing.
  • 1. Scope of work. [Room]: remove [items]. Install [items]. [Items] stay where they are. [Repeat for each room.]
  • 2. Bylaw items. [Work] falls under Bylaw 5(1)[letter]. [Work] falls under Bylaw 6. [Repeat for each part of the work.]
  • 3. Pipes, wires and ducts. The work touches [list each one]. [Each one] serves [this unit only, or other units]. All other pipes, wires and ducts stay as they are.
  • 4. Drawings and products. Attached: a floor plan marked with the changes, and product sheets for [flooring, layer under the flooring, plumbing fixtures].
  • 5. Contractor. [Company name], [contact person], [phone and email]. Attached: [each document the building's bylaws, rules or alteration agreement list].
  • 6. Dates and hours. Planned start: [date]. Planned finish: [date]. Work will take place within the hours set in [bylaw or rule number]: [hours].
  • 7. Common areas. [Covering] will protect the hallway floor and the elevator. Materials will enter through [entrance]. Waste will leave by [route] and go to [place]. I request an elevator booking for [dates].
  • 8. Expenses. Bylaw 5(2) allows the strata to require my written agreement to take responsibility for expenses relating to this alteration. Please send the agreement the strata uses so that I can read and sign it.
  • 9. Reply. Please send the council's written decision to [email and mailing address]. I can attend the council meeting on [date] to answer questions.
  • Signed: [owner's name]

After you send it

Keep a copy of the letter, the attachments and the proof of sending. The strata must keep correspondence sent or received by the strata corporation and council (Act, s. 35(2)(k)), and section 4.1(5) of the regulation sets the period at 2 years or more. Your own file should last as long as you own the unit.

Ask the strata manager which council meeting will consider the request. If the council sends questions, answer each one in writing and number your answers to match.

If the scope changes after approval, write again before the changed work is done. Standard Bylaw 5(1) requires approval before an alteration is made, and the approval you hold covers only the work your letter described.

If a meeting passes and no answer comes, send a hearing request under section 34.1. State the reason: that you seek a decision on the request dated [date]. The council must then hold a meeting to hear you within 4 weeks.

What we prepare for an owner's request

When we work with an owner on a strata renovation, we prepare parts 2 to 8 of the request. We read the building's bylaws, rules and form, then write the scope in the same words our contract uses, so the council approves the work that will be built.

We look at the unit to find which pipes, wires and ducts the work will touch and which of them serve other units. We mark the floor plan, collect the makers' product sheets, and attach the contractor documents the building lists.

The owner reads the package, signs the letter and sends it. We set the start date after the written approval arrives.

Sources

Frequently asked questions

Does a renovation request to a BC strata have to be in writing?

The Standard Bylaws require the strata's approval of a renovation to be in writing, and they set no form for the owner's request. Standard Bylaws 5(1) and 6(1) both say an owner must obtain "the written approval of the strata corporation" before an alteration. A written request is the practical choice, because it sets the scope the approval covers and gives you a dated record. Your building's own bylaws may set an application form.

Where do I send a renovation request so that it counts as given to the strata?

Section 63(1) of the Strata Property Act lists the ways a document can be given to a BC strata corporation: left with a council member, mailed to the strata's most recent address on file in the land title office, emailed or faxed to the strata's address or to one a council member provided for that purpose, or put in the strata's mail slot. A document sent by mail, fax or email is treated as given 4 days later.

How long does a strata have to keep my renovation request and its reply?

A BC strata must keep correspondence sent or received by the strata corporation and its council for at least 2 years. The duty to keep it is in section 35(2)(k) of the Strata Property Act, and the period is in section 4.1(5) of the Strata Property Regulation. You may own the unit for longer than that, so keep your own copy of the renovation request, the approval and any signed agreement.

Can a tenant ask the strata to approve a renovation?

Under the Standard Bylaws, the request to approve a renovation comes from the owner of the unit. Standard Bylaws 5(1) and 6(1) both begin "An owner must obtain the written approval of the strata corporation". A tenant who wants work done should ask the owner to make the request. Section 34.1 of the Strata Property Act does give a tenant, as well as an owner, the right to request a hearing at a council meeting.

Can my contractor send the strata renovation request for me?

A contractor can prepare a strata renovation request, and the owner should sign and send it, because Standard Bylaw 5(1) places the duty on the owner: "An owner must obtain the written approval of the strata corporation". For records, section 36(1) of the Strata Property Act lets a person an owner has authorized in writing obtain copies of the bylaws and rules, so a signed authorization lets a contractor collect those for you.

Should work inside my unit and work on common property go in one request?

One letter can cover both kinds of work, and it should list them under separate headings. Work inside a unit falls under Standard Bylaw 5, which says the strata "must not unreasonably withhold its approval". Work on common property or limited common property falls under Bylaw 6, which leaves that sentence out. Separate headings let a council approve the inside work even if it wants more time on the common property part.

Should my renovation request include the agreement on expenses?

Your renovation request should ask the strata to send the expenses agreement it uses, so that you can read it before the council meets. Standard Bylaw 5(2) lets a BC strata require, as a condition of approval, that the owner agree in writing to take responsibility for any expenses relating to the alteration. Asking in the request gives you time to read it. Read the wording, and get legal advice if it is broader than the bylaw.

Can I change the renovation scope after the strata has approved it?

A change to the renovation scope needs its own written approval when the new work touches anything on the approval list. Standard Bylaw 5(1) requires an owner to obtain written approval "before making an alteration", and the approval you hold covers the work your request described. Write to the council before the changed work is done, describe only what is different, and name the bylaw item it falls under.

How do I get the strata plan to check my unit's boundaries before writing?

Ask your strata in writing for a copy of the registered strata plan. Section 35(2)(b) of the Strata Property Act requires a BC strata to keep the plan and any amendments, and section 36(3) gives it 2 weeks to provide a copy to an owner. Section 4.2 of the regulation limits the copying fee to 25 cents per page. The plan shows the unit, the common property and any limited common property.

What reason should I state when I request a council hearing about my renovation?

State that you are asking for a decision on your renovation request, and give the date you sent it. Section 34.1(1) of the Strata Property Act requires a hearing request to be an application in writing "stating the reason for the request". Naming a decision as the purpose matters under section 34.1(3), which requires a written decision within one week after the hearing when a decision is what the hearing seeks.

Related service

Home Renovation

See how we handle home renovation projects across the North Shore.

Learn about home renovation

Free quote

Get a project estimate

Share a few details and we'll respond within one business day.

Ready to build?

Talk to RealDream Contracting.

Call (604) 401-4849, send an inquiry, or book a consultation to discuss your project on the North Shore.

RealDream × Realtors

Let's build something together.

Leave your details. Let's talk about working together.

An introduction starts the conversation. Partnership terms are agreed together.

Prefer a conversation? (604) 401-4849