The short answer
Nine causes delay a condo renovation in Vancouver: an incomplete strata request, a late council meeting, conditions set after the contract, hazardous materials, a booked elevator, late orders, a water shut-off, a permit still to be issued, and changes made mid-job. After a written hearing request, BC law requires a council to hold the hearing within 4 weeks and decide within one more week.
Nine causes, who controls each, and what to do early
Each cause in the table is controlled by one person or body. That tells you whom to write to, and when.
| Cause | Who controls it | What to do early |
|---|---|---|
| An incomplete strata request | You and your contractor | Get the building's renovation form first, and send every document it lists in one package |
| A council meeting later than the planned start | The strata council | Ask for the next meeting date and the last day to add an agenda item. If no answer comes, send a written hearing request (Strata Property Act, s. 34.1) |
| Conditions set after the contract is signed | The strata council | Have the contract say how a change required by the council is priced and how the dates move |
| Hazardous materials found by the inspection | The qualified person who inspects, then a licensed removal contractor | Book the inspection during design, before the price and the dates are fixed |
| A booked elevator | The building | Ask how far ahead a booking must be made, and book the delivery days when the start date is fixed |
| Ordered items arriving late | The suppliers. You control the day the order is placed | Order the item with the longest wait first. Our published wait for a cabinet order is 8 to 12 weeks |
| A water shut-off the building schedules | The strata | Ask in writing who closes the valve, what notice other owners need and which hours are allowed |
| A permit still to be issued | The City of Vancouver | Ask the City which permits the work needs. The licensed contractors apply for the electrical and gas permits |
| Changes you make mid-job | You | Fix the layout and the products before the request goes to the strata |
The strata: the request, the meeting date and the conditions
An incomplete request. A council approves a described scope with named products. If the request leaves out a document your building's form lists, the council can ask for it, and its answer may then wait for a later meeting. Send one complete package: the scope, the drawings, the product sheets, the contractor's documents, the hazardous materials report and the planned dates.
A meeting after the planned start. Each council sets its own meeting dates. The Strata Property Act sets deadlines once you ask for a hearing. Under section 34.1, an owner may request a hearing at a council meeting by writing to the council and stating the reason. The council must hold a meeting to hear the owner within 4 weeks after the request. If the hearing seeks a decision, the council must give it in writing within one week after the hearing. From the request to the written decision, the longest wait the Act allows is 5 weeks.
Conditions after the contract. An approval can arrive with conditions. Standard Bylaw 5(2) lets the strata require, as a condition, that the owner agree in writing to take responsibility for any expenses relating to the alteration, and a building's own bylaws can add others. A condition that changes a product or a method changes the order and the dates with it. If a council asks for a change, we revise the scope, the price and the schedule together and send them back as one document.
Hazardous materials found by the inspection
Section 20.112 of the Occupational Health and Safety Regulation requires a qualified person to inspect for hazardous materials before renovation work begins. If the report finds asbestos or another hazardous material where the work will disturb it, subsections (7) and (8) stop that work until the material is safely contained or removed and a qualified person has confirmed this in writing. WorkSafeBC states that since January 1, 2024, asbestos abatement contractors, the companies that remove or contain asbestos, must be licensed to operate in BC.
Book the inspection during design. A report that exists before the schedule is written lets the removal be planned as its own stage, with its own dates. A report that arrives after the start date stops work that was already booked.
A suspect material found after demolition starts is handled under subsection (6): a qualified person samples it, identifies it and reports in writing.
The building: the elevator and the water
Materials, tools and waste travel by elevator. The Province of BC's page on common property lists elevators among the parts of a condominium that are typically common property, and section 125(1) of the Act lets the strata make rules governing the use of common property. Where a building requires bookings, a delivery that misses its booked time waits for the next free one. Ask for the booking rules in writing, and ask how far ahead a booking must be made.
Plumbing work that needs a valve serving more than one unit depends on the strata, because section 3 of the Act makes the strata corporation responsible for managing the common property. The strata sets the day and the notice to other owners. We ask for the shut-off dates as soon as the approval arrives, and we schedule the plumbing work on those dates.
Ordered items arriving late
The item with the longest wait sets the earliest date for the work that depends on it. In a kitchen that item is the cabinets, and our published wait for a cabinet order is 8 to 12 weeks.
The day the order is placed is your decision. An order placed before the strata's written approval saves time if the council approves the request unchanged. If the council requires a change to a made-to-measure item, you pay to change the order. We tell you which items can be ordered before the approval letter and which should wait for it.
A permit still to be issued
Inside the City of Vancouver, the City issues electrical and gas permits. Technical Safety BC, the body that runs BC's Safety Standards Act, lists the City among 10 municipalities that issue their own. It says a licensed contractor applies for the permit on the owner's behalf, and it advises owners: "Check to ensure there is one in place before work begins."
The City sets its own processing times. Its website refused our automated requests on October 4, 2026, so this page states no City time. Put the permit question to the City while the council is reading the request, so that the two waits happen at the same time.
Changes you make mid-job
A change after the work starts can affect three things at once: the strata's approval, an order already placed and the booked dates. Standard Bylaw 5(1) requires an owner to obtain written approval "before making an alteration", and the approval you hold covers the work the request described. A change that touches anything on the approval list goes back to the council before it is built.
Decide the layout, the flooring, the fixtures and the appliances before the request goes in. If you want a change later, we give you its price and its effect on the dates in writing before any work on it starts.
How we report a delay
We write the schedule as a list of dated stages, and we mark which dates depend on the council, the City, the building or a supplier. When one of those dates moves, we send a revised schedule that names the cause.
Sources
- Strata Property Act, SBC 1998, c. 43 (sections 3, 34.1, 125 and 130), read October 4, 2026
- Strata Property Act, Schedule of Standard Bylaws (Bylaw 5), read October 4, 2026
- Strata Property Regulation, B.C. Reg. 43/2000 (section 7.1, maximum fines), read October 4, 2026
- Civil Resolution Tribunal Act, SBC 2012, c. 25 (section 121), read October 4, 2026
- Civil Resolution Tribunal, Strata Property, read October 4, 2026
- Province of BC, Common property and limited common property, read October 4, 2026
- Occupational Health and Safety Regulation, B.C. Reg. 296/97, Part 20 (section 20.112, hazardous materials), read October 4, 2026
- WorkSafeBC, Asbestos training, certification and licensing, read October 4, 2026
- Technical Safety BC, Homeowner Electrical Permits, read October 4, 2026
- Technical Safety BC, Jurisdiction, read October 4, 2026
Frequently asked questions
Can a hearing request get a strata decision before my planned renovation start date?
A written hearing request puts a legal deadline on a strata council's decision about a renovation. Under section 34.1 of the Strata Property Act, the council must hold a meeting to hear the owner within 4 weeks after the request, and if the hearing seeks a decision, must give a written decision within one week after the hearing. Count 5 weeks back from your planned start date, and send the request before that day if the council has given no answer.
Can a strata add conditions after I have signed a renovation contract?
Yes, a strata's conditions arrive with its approval, whatever date the renovation contract was signed. Standard Bylaw 5(2) lets a BC strata require, as a condition of approval, that the owner agree in writing to take responsibility for any expenses relating to the alteration, and a building's own bylaws can add other conditions. Ask the contractor to write into the contract how a change required by the council is priced and how the start date moves.
Does all work stop in a condo if asbestos is found in one room?
BC's regulation stops the work that may disturb the asbestos found in a condo. Section 20.112(7) of the Occupational Health and Safety Regulation says no renovation work that may disturb the identified hazardous materials may be carried out until they are safely contained or removed, and subsection (8) requires a qualified person to confirm that in writing. We ask the qualified person who wrote the report, in writing, which other work can continue, and we follow that answer.
Can a missed elevator booking delay a condo renovation?
Yes, a missed elevator booking can delay a condo renovation where the building requires bookings, because the delivery waits for the next free time. The Province of BC's page on common property lists elevators among the parts of a condominium that are typically common property, and section 125(1) of the Strata Property Act lets the strata make rules governing the use of common property. Ask the strata manager in writing how far ahead a booking must be made.
How much notice does a building need to shut off water for a condo renovation?
Each building sets its own notice period for a water shut-off during a condo renovation, so ask the strata manager in writing. Section 3 of the Strata Property Act makes the strata corporation responsible for managing and maintaining the common property, and a pipe that supplies water to more than one unit is common property under section 1. We ask for the shut-off dates as soon as the strata's approval arrives, and we schedule the plumbing work on those dates.
Can the strata fine me if my condo renovation runs past the dates it approved?
A strata can fine an owner for contravening a bylaw or a rule, so the answer depends on whether your building's bylaws, rules or approval conditions set an end date for a condo renovation. Under section 7.1 of the Strata Property Regulation, the most a strata may set in its bylaws is $200 for each contravention of a bylaw, and a continuing contravention can be fined at most every 7 days. Write to the council before the approved dates pass and ask for new ones.
Can I file a tribunal claim if a slow strata approval delays my condo renovation?
Yes, the Civil Resolution Tribunal can hear a claim about how a strata applied the Strata Property Act or its bylaws to a renovation request. Section 121(1) of the Civil Resolution Tribunal Act gives it that jurisdiction. The tribunal's Strata Property page said on October 4, 2026 that it can take several months for an application to be reviewed, so send a written hearing request under section 34.1 of the Strata Property Act first. The council must hear it within 4 weeks.
Does RealDream set a start date before the strata approves a condo renovation?
We set the start date of a condo renovation after the strata's written approval arrives and the permit question is settled with the City. Standard Bylaw 5(1) requires an owner to obtain the strata's written approval before making an alteration on its list, so demolition waits for the approval letter. Before that day we give a schedule of dated stages that marks which dates depend on the council and on the City.