The short answer
Plan to live elsewhere when a condo renovation closes the only bathroom, removes the kitchen, or removes asbestos or another hazardous material. BC's Occupational Health and Safety Regulation, section 20.112, stops renovation work that may disturb a hazardous material until a qualified person confirms in writing that it is contained or removed. Flooring, painting, or one bathroom of two can be done while you stay.
Which work means moving out
The test is simple: at the end of each working day, does the unit have a toilet, a shower, a sink and a place to sleep that is free of dust? If the answer is no, plan to live elsewhere for that period.
The table applies that test to common scopes. The two durations are figures we published for houses on the North Shore. A condo adds the building's limits on working hours.
| Work | What the unit is without | Stay or leave |
|---|---|---|
| The only bathroom, rebuilt | Toilet and shower. Our published time for a single bathroom in a house is 4 to 6 weeks from demolition to completion. | Leave |
| One bathroom of two | One toilet and shower. The other bathroom stays in use. | Stay |
| A full kitchen | Sink, cooking and counters. Our published time for a kitchen with permits in a house is 10 to 16 weeks from demolition to completion. | Leave, or stay with meals arranged outside the unit |
| New flooring through the whole unit | Each room in turn, while its floor is replaced. Furniture has to be moved out of each room before its floor is replaced. | Stay if the furniture can move room to room, leave if it cannot |
| Painting | Each room in turn. | Stay |
| Removal of asbestos or another hazardous material | The rooms where the removal takes place, until the written confirmation described below. | Leave |
Hazardous materials: the unit stays closed until removal is confirmed
Section 20.112 of the Occupational Health and Safety Regulation requires a qualified person to inspect for hazardous materials before renovation work begins. If the report finds asbestos or another hazardous material in the areas the work will disturb, subsections (7) and (8) apply. Renovation work that may disturb the material waits until it is safely contained or removed, and a qualified person confirms that in writing.
WorkSafeBC's page on testing a home for asbestos gives the reason in one sentence: "Exposure to airborne asbestos can cause serious health issues for anyone working or living on your property." Its page on asbestos adds that a qualified person must certify that the worksite air is safe after the removal.
We ask owners to be out of the unit from the day removal starts until that written confirmation arrives. The confirmation is kept in the unit with the inspection report, as section 20.112(4) requires.
Dust from tile and concrete
Cutting tile or concrete releases silica dust. WorkSafeBC says the dust can cause silicosis, a lung disease that cannot be reversed.
The regulation's rules on silica protect workers. Section 6.112(2) requires a risk assessment by a qualified person before the work, and section 6.112.2 puts dust reduction systems and containment first among the controls. The regulation's list of dust reduction systems includes an enclosure, ventilation that captures dust at the tool, and water that keeps dust out of the air.
If you stay in the unit, ask your contractor which of those controls will be used. We close the work area off from the rooms you live in and clean the path to the unit door at the end of each working day.
Days without water
Plumbing work needs the water off. If the unit has its own working shut-off valve, the water is off in your unit alone. If the work needs a valve that also supplies other units, the strata arranges the shut-off, because section 3 of the Strata Property Act makes the strata corporation responsible for managing the common property.
On a shut-off day the unit has no tap, toilet or shower for the hours the valve is closed. We give you each shut-off date in writing before the work starts, so you can plan to be out on those days if you are living in the unit.
What the Province says about insurance, an empty unit and a place to stay
The Province of BC's page on strata owner insurance says the strata corporation's policy leaves out the expenses of owners who have to live elsewhere after a loss. It describes the matching cover in an owner's own policy as additional living expenses "in the event of an insured loss", and its example is a fire.
A renovation you plan is your own decision, and we found no source that says insurance pays for a place to stay during one. Budget for the stay yourself, and ask your broker to confirm in writing.
The same page lists insurance for a unit that is "left vacant for periods of time" among the other cover an owner can buy, beside cover for major upgrades done to the unit. It also says that after a change in insured property it is important to contact the insurance broker and the strata council immediately. Ask the broker these questions before you move out:
- Does my policy stay in force while the unit is empty and under renovation, and for how many days?
- Does the policy ask for someone to check the unit while it is empty, and how often?
- Does my cover for the strata's deductible apply during the work?
- What limit should the policy carry for the new kitchen, bathroom or flooring once the work is done?
While you are away, the strata still has to reach you
Give the strata manager a mailing address outside the building, in writing, before you leave. Under section 61 of the Strata Property Act, a strata that holds an outside address for an owner gives its notices by handing them to the owner or by mailing them to that address. A strata that holds no outside address may put a notice under the unit door, and the Act treats that notice as given 4 days later. A complaint about the work could lie unread on the floor of an empty unit.
Tell the strata who holds a key. Standard Bylaw 7 lets a person authorized by the strata enter a unit in an emergency without notice, and at a reasonable time on 48 hours' written notice to inspect or repair common property.
Furniture and belongings
A room under renovation has to be empty. For flooring through the whole unit, that is every piece of furniture, one room at a time or all at once.
Three places can hold furniture: another room of the unit, the storage locker allocated to your unit if it has one, and rented storage outside the building. Space in a hallway, a service room or the parking area is common property. Section 76 of the Act lets a strata give an owner permission to use common property exclusively, so ask in writing before anything is left there.
How we stage the work when you stay
Where a unit has two bathrooms, we rebuild one at a time. The second bathroom stays in use until the first has a working toilet, sink and shower again.
We tell you at the quote stage which rooms will be closed and for how long in your building. The schedule names the days when water will be off and the days when hazardous materials are removed.
Sources
- Occupational Health and Safety Regulation, B.C. Reg. 296/97, Part 20 (section 20.112, hazardous materials), read October 4, 2026
- Occupational Health and Safety Regulation, B.C. Reg. 296/97, Part 6 (sections 6.110 to 6.112.2, silica), read October 4, 2026
- WorkSafeBC, Have your home tested for asbestos before reno, demo, or maintenance work, read October 4, 2026
- WorkSafeBC, Asbestos, read October 4, 2026
- WorkSafeBC, Silica, read October 4, 2026
- Province of BC, Strata owner and tenant insurance (published July 23, 2025), read October 4, 2026
- Strata Property Act, SBC 1998, c. 43 (sections 3, 61 and 76), read October 4, 2026
- Strata Property Act, Schedule of Standard Bylaws (Bylaw 7), read October 4, 2026
Frequently asked questions
Do I have to move out of my condo while asbestos is removed?
Plan to be out of the condo from the day asbestos removal starts until a qualified person confirms in writing that the material is contained or removed. Section 20.112 of BC's Occupational Health and Safety Regulation requires that written confirmation before renovation work that may disturb the material continues. WorkSafeBC says exposure to airborne asbestos can cause serious health issues for anyone working or living on the property.
Can I stay in a two-bathroom condo while one bathroom is renovated?
Yes, an owner can stay in a two-bathroom condo while one bathroom is renovated, because the other toilet and shower stay in use. Our published time for a single bathroom in a North Shore house is 4 to 6 weeks from demolition to completion, and a condo adds the building's limits on working hours. We rebuild one bathroom at a time and start the second after the first works again.
Will my condo insurance stay valid if the unit is empty during a renovation?
Only your broker can confirm that your condo insurance stays valid while the unit is empty during a renovation. The Province of BC's page on strata owner insurance lists cover for a unit "left vacant for periods of time" among the other cover an owner's policy can include, beside cover for major upgrades done to the unit. Ask the broker in writing how many days the unit may be empty and what the policy asks of you during that time.
Where will the strata send a notice if I have moved out during my condo renovation?
The strata will mail a notice to the outside address you gave it, or leave it at the unit if you gave none. Section 61 of the Strata Property Act lets a BC strata put a notice under the unit door when it holds no outside address for the owner, and the notice counts as given 4 days later. Give the strata manager a mailing address outside the building in writing before you leave for the renovation.
Can I store furniture in my condo building's hallway or parking stall area during a renovation?
Furniture can be stored on a condo building's common property only with the strata's permission. Section 76 of the Strata Property Act lets a BC strata give an owner permission to exclusively use common property, and the permission can carry conditions and lasts for a period of up to one year. Ask in writing before leaving anything in a hallway, a service room or the parking area, and use your own storage locker first.
How long is a condo without a kitchen during a full kitchen renovation?
A condo is without its kitchen from demolition until the sink, counters and appliances are connected again. Our published time for a kitchen renovation with permits in a North Shore house is 10 to 16 weeks from demolition to completion, and a condo adds the building's limits on working hours and elevator bookings. We give the closed period for your building at the quote stage, before you book a place to stay.
Is it safe to sleep in a condo where tile or concrete was cut that day?
Sleeping in a condo after tile or concrete was cut depends on how the dust was controlled, so ask the contractor before the work starts. WorkSafeBC says cutting concrete or stone releases silica dust, which can cause silicosis, a lung disease that cannot be reversed. Section 6.112.2 of BC's Occupational Health and Safety Regulation puts dust reduction systems and containment first among the controls an employer must apply.
Who should I tell before I leave my condo empty for a renovation?
Tell your insurance broker and the strata before you leave a condo empty for a renovation. The Province of BC's page on strata owner insurance says that after a change in insured property and assets it is important for the owner to contact the insurance broker and the strata council immediately. Give the strata manager your outside mailing address and the name of the person who holds a key while you are away.