The short answer
A concrete condo ceiling is part of the building's structure, so cutting into it for lights needs the strata's written approval under Standard Bylaw 5(1)(a). Five options leave the concrete uncut: a lowered ceiling section, surface-mounted fixtures and track, wall lights, lamps on switched outlets, and under-cabinet lighting. New wiring needs a licensed electrical contractor and a permit, which the City issues in Vancouver.
Why a concrete ceiling is structure
Where a condo's ceiling is a concrete slab, the same slab is the floor of the unit above. Section 68(1) of the Strata Property Act puts the boundary between the two units midway through the structural part of that ceiling, unless the strata plan shows another line. The lower half is inside your unit and the upper half is inside your neighbour's.
The slab is also part of the building's structure. Standard Bylaw 5(1)(a) requires the strata's written approval before an owner makes an alteration that involves the structure of a building. A groove cut for a cable, or a hollow cut for a light, is an alteration of that kind. We treat a concrete ceiling as structure until the building's drawings say otherwise.
Wires inside the slab belong to the building. Section 1 of the Act defines common property to include wires and cables for electricity that are located within a ceiling that forms a boundary between two units. If the wire that feeds your existing ceiling light runs inside the concrete, that length of it is common property, and Standard Bylaw 6 requires written approval to alter common property.
Drilling raises the same questions as cutting. A fixture fixed to a concrete ceiling hangs from anchors drilled into the slab, so we name the anchors in the request to the strata. BC's Occupational Health and Safety Regulation lists using power tools to cut, grind or drill concrete as a silica process (section 6.110), and section 6.112(2) requires a risk assessment by a qualified person before workers do work that may expose them to the dust.
Five options that leave the concrete uncut
Each option in the table brings light to a new place while the slab stays whole.
A lowered ceiling section is a frame covered with drywall and fixed below the concrete over part of a room, such as a hallway or a kitchen. It gives a space for cable and for lights set into the new surface. It also brings the ceiling down over that area, so we mark its edges on the walls for you to see before anything is built.
Under the Standard Bylaws, replacing an original attached light fixture needs the strata's written approval, because section 9.1(1) of the Strata Property Regulation counts electrical fixtures as fixtures and Bylaw 5(1)(g) covers the fixtures the developer installed. A lamp that plugs in is attached to nothing and falls outside that definition.
| Option | How power reaches it | What to settle first |
|---|---|---|
| A lowered ceiling section | New cable runs in the space between the new drywall surface and the concrete | Where the frame is fixed, what it covers, and whether a sprinkler head or a smoke alarm sits in that area |
| Surface-mounted fixtures and track | From an existing electrical box in the ceiling. The track carries power along the surface to each light | The anchors into the concrete, and how much the existing wiring can supply |
| Wall lights | Cable inside a wall that stands wholly within the unit | Whether that wall holds pipes, wires or ducts that serve other units |
| Lamps on switched outlets | The lamp plugs into an outlet that a wall switch turns on and off | An electrical permit, if an outlet or a switch is added or moved |
| Under-cabinet lighting | From the kitchen's wiring, with the cable hidden by the cabinets | The positions, before the cabinets are ordered |
Have the ceiling coating tested first
Section 20.112 of the Occupational Health and Safety Regulation requires the employers responsible for a renovation, and the owner, to ensure that a qualified person inspects for hazardous materials before the work begins. WorkSafeBC lists textured ceiling coat among the building materials that often contained asbestos, and says a home built before 1990 is likely to contain some asbestos.
The ceiling's coating is sampled before anyone scrapes it, drills through it or fixes a frame to it.
Sprinkler heads and smoke alarms stay where they are
If your unit has fire sprinkler heads or a smoke alarm on the ceiling, treat each one as a fixed point of the lighting plan. We move, cover, paint or enclose one of them only with the building's written approval.
These parts can belong to the building. The Act's definition of common property includes a pipe for water inside a unit when it is capable of being used, and intended to be used, by another unit or the common property. We read a sprinkler pipe that serves more than one unit as meeting that test. The Strata Property Regulation names fire protection among the building's systems that a depreciation report must describe (section 6.2). Ask the strata in writing whether the alarm in your unit is connected to the building's fire alarm system, and who is allowed to work on it.
We state no building code rule about sprinklers or alarms on this page. The Province of BC says: "BC Codes don't apply in the City of Vancouver which has its own building bylaw." The City's website refused our automated requests on October 4, 2026, so we could read none of its pages. If a lowered ceiling section would stand near a sprinkler head, our request to the strata shows that head, and any change to it is made by the company the strata names.
Electrical permits and the licensed contractor
Technical Safety BC, the body that runs BC's Safety Standards Act, lists "replacing light fixtures or ceiling fans" and "installing or moving light switches or electrical outlets" among the work that needs an electrical permit. It states that owners of a strata "cannot obtain homeowner permits and must hire a licensed contractor", and that the contractor applies for the permit on the owner's behalf.
Those are Technical Safety BC's rules for its own area. The City of Vancouver is one of 10 municipalities that issue their own electrical permits, so the permit for a Vancouver condo comes from the City. Ask the electrical contractor to show you the permit before the work starts.
The building's electrical capacity
The Province of BC's page on electrical planning reports says almost all strata corporations have finite electrical capacity. It adds that when an owner wants to add equipment that will increase the electrical demand, the strata needs to ensure a qualified professional selects the equipment and confirms the electrical capacity.
For a lighting plan, we give the electrical contractor a list of every new fixture and the power it draws, taken from the maker's product sheet. The contractor checks the list against what the unit's electrical panel can supply, and we put the contractor's written answer in the strata request.
How we plan lighting under concrete
We start from what exists. Each electrical box in the ceiling, each switch and each outlet goes on the plan first. Then we place new light where one of the five options can reach. Where no option can reach a place without cutting concrete, we tell you so and show the nearest alternative.
Before a lowered ceiling section is closed, we photograph the cables and boxes inside it for your file.
Sources
- Strata Property Act, SBC 1998, c. 43 (sections 1 and 68), read October 4, 2026
- Strata Property Act, Schedule of Standard Bylaws (Bylaws 5 and 6), read October 4, 2026
- Strata Property Regulation, B.C. Reg. 43/2000 (sections 6.2 and 9.1), read October 4, 2026
- Occupational Health and Safety Regulation, B.C. Reg. 296/97, Part 6 (sections 6.110 and 6.112, silica), read October 4, 2026
- Occupational Health and Safety Regulation, B.C. Reg. 296/97, Part 20 (section 20.112, hazardous materials), read October 4, 2026
- WorkSafeBC, Have your home tested for asbestos before reno, demo, or maintenance work, read October 4, 2026
- Technical Safety BC, Homeowner Electrical Permits, read October 4, 2026
- Technical Safety BC, Jurisdiction, read October 4, 2026
- Province of BC, Strata electrical planning report (published June 5, 2026), read October 4, 2026
- Province of BC, BC Building Code 2024, read October 4, 2026
Frequently asked questions
Can I install recessed pot lights in a concrete condo ceiling?
Recessed lights, also called pot lights, can go into the concrete itself only by cutting the building's structure. Standard Bylaw 5(1)(a) requires the strata's written approval for an alteration that involves the structure of a building, and under section 68(1) of the Strata Property Act the upper half of that slab is inside the unit above. The option that keeps the concrete whole is a lowered ceiling section, with the lights set into its drywall surface.
Is the wiring inside my concrete condo ceiling common property?
Yes, wiring inside a concrete ceiling that separates two condos is common property under BC law. Section 1 of the Strata Property Act includes wires and cables for electricity located within a floor, wall or ceiling that forms a boundary between a strata lot and another strata lot. Standard Bylaw 6 requires the strata's written approval before an owner alters common property, and it lacks the sentence in Bylaw 5 that stops a strata from unreasonably withholding approval.
Does adding a track light to an existing ceiling box need an electrical permit?
Under Technical Safety BC's rules, replacing a light fixture is electrical work that needs a permit, and a track light fitted to an existing ceiling box replaces the fixture that was there. Its homeowner electrical page lists "replacing light fixtures or ceiling fans" among its examples. A strata owner must hire a licensed contractor, who applies for the permit. Inside the City of Vancouver the City issues electrical permits, so confirm the requirement with the City.
Can I drill into a concrete condo ceiling to hang a light fixture?
Ask the strata in writing before drilling into a concrete condo ceiling. The slab is structure, which Standard Bylaw 5(1)(a) covers, and wires located inside a boundary ceiling are common property under section 1 of the Strata Property Act, so a drill can reach something the building owns. BC's Occupational Health and Safety Regulation lists drilling concrete with power tools as a silica process in section 6.110, and section 6.112(2) requires a risk assessment before workers do it.
Can I move a sprinkler head to fit a lowered ceiling in my condo?
A sprinkler head in a condo should be moved only with the strata's written approval, by the company the strata names. Under section 1 of the Strata Property Act, a water pipe inside a unit is common property when it is capable of being used, and intended to be used, by another unit or the common property, and Standard Bylaw 6 requires approval before an owner alters common property. We plan a lowered ceiling section around the sprinkler heads.
Does a textured condo ceiling need testing before lights are added?
Yes, have a textured condo ceiling sampled before any work scrapes it or drills through it. Section 20.112 of BC's Occupational Health and Safety Regulation requires the employers responsible for a renovation, and the owner, to ensure that a qualified person inspects for hazardous materials before the work begins. WorkSafeBC lists textured ceiling coat among the building materials that often contained asbestos, and says a home built before 1990 is likely to contain some.
Does a lowered ceiling section in a condo need strata approval?
A lowered ceiling section needs the strata's written approval under the Standard Bylaws when it is fixed into the concrete slab, covers common property or changes the original light fixtures. Standard Bylaw 5(1) names the structure in item (a), common property inside the unit in item (f) and the developer's original fixtures in item (g). Your building's own bylaws can add a rule on ceilings, so we include the lowered ceiling section in every request.
Will new lighting exceed my condo building's electrical capacity?
Whether new lighting fits a condo building's electrical capacity is for a qualified professional to confirm. The Province of BC says almost all strata corporations have finite electrical capacity, and that when an owner wants to add equipment that will increase electrical demand, the strata needs to ensure a qualified professional selects the equipment and confirms the capacity. We give the electrical contractor a list of the new fixtures and the power each one draws, from the makers' product sheets.
Related service
Condo Renovation
See how we handle condo renovation projects across the North Shore.
Learn about condo renovationRelated articles