The West End's Older Strata Buildings by the Numbers, and What to Ask Before You Renovate

The West End is one of the City of Vancouver's 22 local areas, and the City's 2026 property tax report lists 9,888 strata lots inside its boundary. This page sets out when those lots were built, five years at a time, which zoning codes the older ones fall under, what the 1990 line in WorkSafeBC's asbestos guidance means for them, and the three documents to request from the strata before any design work.

By Nima Gerani, Founder, RealDream Contracting
December 3, 2026 7 min read

The short answer

Of the 9,888 strata lots in Vancouver's West End local area, 4,242 (42.9 percent) carry a year built before 1990 on the City's 2026 tax roll, and 4,026 of those were built between 1970 and 1989. WorkSafeBC says a home built before 1990 is likely to contain some asbestos. Before planning, request the depreciation report, the electrical planning report and the council minutes from the strata.

Note: The counts were read on October 4, 2026 from data the City refreshes weekly. The year built is the one BC Assessment assigns from permit records. Section numbers and page wording were read the same day and can change. This is general information from a renovation contractor.

What one record is

The City's property tax report holds one record per property on the tax roll, identified by a BC Assessment folio number. A record whose legal type is STRATA is one strata lot. The report has no field for how a lot is used, so the counts below cover every type of strata lot, homes included.

Each record carries a year built, which the City describes as "Year that the property was built. Assigned by BCA based on permit records". We placed each record in a local area by matching its land coordinate, the first 8 digits of the folio number, to the same key in the City's property addresses data.

West End strata lots by period built

The 9,888 lots sit on 211 properties, an average of 46.9 lots per property. The 4,242 lots built before 1990 sit on 119 of those properties, which is 56.4 percent of them.

The 1970s and 1980s hold 4,026 lots between them. Split five years at a time, the count rises through the period: 671 lots from 1970 to 1974, 729 from 1975 to 1979, 1,271 from 1980 to 1984 and 1,355 from 1985 to 1989.

Strata lots in the West End local area by year built, City of Vancouver 2026 property tax report (read October 4, 2026)
Year built Strata lots Share of 9,888
Before 1950 193 2.0 percent
1950 to 1969 23 0.2 percent
1970 to 1979 1,400 14.2 percent
1980 to 1989 2,626 26.6 percent
1990 to 1999 3,141 31.8 percent
2000 to 2009 962 9.7 percent
2010 to 2019 601 6.1 percent
2020 or later 170 1.7 percent
No year on the record 772 7.8 percent
Total 9,888 100 percent

The most common single years

The year 1998 is the most common, with 855 lots, followed by 1999 with 606 and 1974 with 504. The year 1990 itself has 413 lots. The oldest year on any West End strata record is 1900.

The 413 lots dated 1990 fall outside the "before 1990" count. WorkSafeBC says asbestos "was widely used in B.C. as a building material until the early 1990s", so we plan a 1990 building the same way as a 1989 one: the inspection described below decides.

Which zoning codes the older lots fall under

The tax report prints a zoning district code on each record. Of the 4,242 lots built before 1990, 1,475 carry the code RM-5A, 1,339 carry RM-5B and 651 carry RM-5. Another 382 are in numbered CD-1 districts, 319 carry DD, 41 carry C-6, 23 carry C-5 and 12 carry RM-5C. Those eight groups add to 4,242.

So 3,465 of the older lots, 81.7 percent, sit in the three codes RM-5, RM-5A and RM-5B. The City's zoning data shows those codes in the West End local area and in no other. Each code has its own district schedule in the City's Zoning and Development By-law, which the City publishes; we state no rule from it here.

What BC Assessment's improvement year adds

Each record also carries a "big improvement year", which the City describes as the "Year of major improvement to the property. Assigned by BCA based on permit records". For 3,770 of the 4,242 older lots (88.9 percent) that year equals the year built. For the other 472 (11.1 percent) it is later: before 1990 for 358 of them, in the 1990s for 108, and in 2000 or later for 6.

A later improvement year tells you that BC Assessment recorded a major permitted improvement on the property. The field names no work, so the strata's own records, described below, hold what was done.

The 1990 line in WorkSafeBC's guidance, and the inspection duty

WorkSafeBC's page on testing a home before renovation says: "if your home was built before 1990, it's likely that at least some parts of the home will contain asbestos that could be released with any renovation, demolition, or maintenance work." The page addresses homeowners, strata councils and property managers, and names drywall, textured ceiling coat, insulation, vinyl flooring and window putty among the materials that often contained asbestos.

The duty to check is in law for a building of any age. Section 20.112(2) of BC's Occupational Health and Safety Regulation says that before renovation work begins, "all employers responsible for that work, and the owner, must ensure that a qualified person inspects" the building and the worksite to identify hazardous materials. The duty sits on the employers and the owner together. The qualified person takes samples and writes a report that gives the location and approximate quantity of each hazardous material found, and that report stays at the worksite while workers are on site.

If the report finds material that the work would disturb, subsections (7) and (8) stop that work until the material is contained or removed and a qualified person confirms it in writing. Since January 1, 2024, a contractor who removes asbestos in BC must hold a WorkSafeBC licence.

The West End's heritage register entries

The City's heritage sites data, in an extract dated March 24, 2023, lists 135 heritage buildings in the West End local area. The data groups them as 27 in evaluation group A, 93 in B and 15 in C, and says to consult the Vancouver Heritage Register for what the letters mean. It marks 39 of the 135 as having a municipal designation, 6 as covered by a heritage revitalization agreement, and 3 as having an interior designation.

A municipal designation is made by by-law under section 593 of the Vancouver Charter. Where a building is designated, the exterior and the structure cannot be altered without a heritage alteration permit, and the same applies to any interior feature or fixture the by-law identifies. Ask the strata whether the building is designated and, if so, for a copy of the by-law.

Three documents to request from the strata before planning

All three exist by law in a strata with five or more lots, and section 36 of the Strata Property Act gives an owner the right to copies of the records the strata must keep, within 2 weeks of a written request. We read all three, look up the year built and the improvement year, and arrange the hazardous materials inspection before a price is fixed.

  • The depreciation report. Section 94(2) of the Act requires one from a qualified person, and the Province says it is due on a five-year cycle. Regulation section 6.2 requires it to describe, with an estimated service life over 30 years, the building's structure, exterior, and systems, including "the electrical, heating, ventilation, air conditioning, plumbing, fire protection and security systems". In a 1970s or 1980s building it shows which pipes and wiring the strata plans to renew, and when.
  • The electrical planning report. The Province requires a strata with five or more lots in Metro Vancouver to obtain one by December 31, 2026. It gives the system's current capacity, existing demands and spare capacity. The Province adds that the report "cannot inform the installation of electrical loads", so a qualified professional still confirms capacity for a new oven, heat pump or in-suite laundry.
  • The council minutes. Section 35(1)(a) requires the strata to keep minutes of general meetings and council meetings, including the results of votes. Minutes show earlier alteration requests in the building and any pipe, window or electrical work the council has discussed.

Sources

Frequently asked questions

Which single year built is most common among West End strata lots?

The year 1998 is the most common year built among West End strata lots, with 855 of the area's 9,888 lots on the City of Vancouver's 2026 property tax report. The next are 1999 with 606 lots and 1974 with 504. The year 1990 itself has 413 lots. The year built is the one BC Assessment assigns from permit records, and 772 West End strata records carry no year at all.

How many West End strata buildings date from the 1970s and 1980s?

The City's 2026 property tax report places 4,026 West End strata lots in the years 1970 to 1989, and the 4,242 lots built before 1990 sit on 119 of the area's 211 strata properties. Counted five years at a time, the lots run 671 from 1970 to 1974, 729 from 1975 to 1979, 1,271 from 1980 to 1984 and 1,355 from 1985 to 1989. A property here is one land coordinate, the first 8 digits of the assessment folio number.

Which zoning codes hold the West End's pre-1990 strata lots?

Three zoning codes hold 3,465 of the West End's 4,242 pre-1990 strata lots, which is 81.7 percent: RM-5A with 1,475, RM-5B with 1,339 and RM-5 with 651, on the City of Vancouver's 2026 property tax report. The rest are 382 in numbered CD-1 districts, 319 under DD, 41 under C-6, 23 under C-5 and 12 under RM-5C. Each code has a district schedule in the City's Zoning and Development By-law.

How many West End strata lots carry a year built of 1990 or earlier?

On the City of Vancouver's 2026 property tax report, 4,655 West End strata lots carry a year built of 1990 or earlier: the 4,242 built before 1990 plus the 413 dated 1990 itself. That is 47.1 percent of the area's 9,888 lots. WorkSafeBC says asbestos was widely used in BC as a building material until the early 1990s, so we plan the hazardous materials inspection the same way for a 1990 building as for an older one.

Does a West End building dated 1990 fall under WorkSafeBC's asbestos warning?

WorkSafeBC's warning names homes built before 1990, and a building dated 1990 sits one year outside that line. The same body says asbestos was widely used in BC as a building material until the early 1990s, and the City's 2026 tax report gives 413 West End strata lots a year built of 1990. We plan for those lots the way we plan for 1989 ones: the hazardous materials inspection report decides what the surfaces contain.

What does BC Assessment's improvement year tell me about an older West End condo?

BC Assessment's improvement year records the year of a major permitted improvement to the property, as the City of Vancouver's tax report describes the field. For 3,770 of the West End's 4,242 pre-1990 strata lots the improvement year equals the year built, and for 472 it is later, including 108 in the 1990s and 6 in 2000 or later. The field names no work, so ask the strata which permitted work the year refers to.

How many West End heritage buildings carry an interior designation?

Three West End heritage buildings carry an interior designation in the City of Vancouver's heritage sites data, extract dated March 24, 2023, out of 135 heritage buildings in the local area. The same data marks 39 of the 135 as having a municipal designation and 6 as covered by a heritage revitalization agreement. Under section 593 of the Vancouver Charter, an interior feature named in a designation by-law cannot be altered without a heritage alteration permit.

Which strata documents should a West End owner request before drawing a renovation plan?

Request the depreciation report, the electrical planning report and the council minutes before drawing a plan for a West End condo. Section 36 of BC's Strata Property Act requires the strata to provide copies of its records within 2 weeks of a written request. The depreciation report describes the building's plumbing and electrical systems with an estimated service life over 30 years, and the electrical planning report gives the building's spare electrical capacity.

Related service

Condo Renovation

See how we handle condo renovation projects across the North Shore.

Learn about condo renovation

Free quote

Get a project estimate

Share a few details and we'll respond within one business day.

Ready to build?

Talk to RealDream Contracting.

Call (604) 401-4849, send an inquiry, or book a consultation to discuss your project on the North Shore.

RealDream × Realtors

Let's build something together.

Leave your details. Let's talk about working together.

An introduction starts the conversation. Partnership terms are agreed together.

Prefer a conversation? (604) 401-4849